Phase 1 is on the brink of being substantially complete! The contractor is planning to finish the seeding on Saturday the 9th. Once the seeding is compliant and in place, Phase 1 will be substantially complete. The PDF attached to this construction update is a Lawn Maintenance Guide which is to serve as a guide for the establishment and care of the newly planted seed. If you have any questions regarding your lawn, please do not hesitate to call Josh at 605-759-6158.
Concrete work in Phase 2 will continue throughout the rest of this week into next week. The contractor is estimating that concrete work will be complete in the middle of next week. The concrete work will be followed by final grading and 5" of Asphalt.
The underdrain is the final utility in Phase 3. Once the underdrain is complete, the contractor will begin to bring in 12" of gravel which will be followed by concrete and asphalt. The underdrain is estimated to be complete early next week.
In Phase 5, the contractor will be tying in water services early next week once the underdrain is complete in Phase 3. The water services will roughly take about a day and a half to tie in. As soon as the water services are tied in, the contractor will begin on storm sewer throughout Phase 5.
If you have any questions regarding this project, please do not hesitate to call Josh at (605)-759-6158.