Throughout this week the contractor has been wrapping up Phase 2. The contractor is estimating that Phase 2 will be substantially complete by the end of next week as a little bit of concrete needs to get finished up followed by top soil. Traffic control will be setup next week while the contractor is placing top soil for safety.
The bottom lift of asphalt in Phase 3 was complete at the end of last week. The top lift will be followed once all of the concrete work is finished. The concrete approaches, driveways, and sidewalks are estimated to take 2 weeks to complete.
Unclassified excavation will start at the beginning of next week followed by the underdrain which is the final utility in Phase 5. Once the underdrain is complete, the contractor will place 12" of aggregate base course and prepare it for curb and gutter. The contractor is estimating that the curb and gutter in Phase 5 will begin in 2 weeks.
If you have any questions or concerns regarding this project, please do not hesitate to call Josh at (605)-759-6158.
2" Top lift of Asphalt located on First Avenue in Phase 2.
Kommentare