September 1st Construction Update

Topsoil will finish today in Phase 1. Temporary traffic control will be set as the contractor moves throughout the phase. The contractor is estimating that seeding will begin next week to wrap up Phase 1.


Curb and gutter in Phase 2 will be completed today. As soon as they complete the curb and gutter, concrete will begin forming up driveways and approaches. The contractor is estimating to have the concrete work complete in 2 weeks. Once the concrete work is complete, gravel will be shaped to grade followed by asphalt.


The contractor will start on the underdrain next week Wednesday in Phase 3 and it is estimated to take about 2 days to finish. Gravel will begin once the underdrain is complete followed by concrete work.


Phase 5 utilities started at the beginning of this week. Sanitary sewer will be completed today which will be followed by watermain. There will be a water shutdown in Phase 5 to tie into the existing watermain in the Boynton and Cedar intersection. Door hangers will be handed out today for houses that will be without water. The East Bound Lane will be closed in the Cedar St and Boynton Avenue intersection during the watermain tie in. The lane closure is expected to be closed for the first half of the day on Tuesday.


If you have any questions or concerns please contact Josh at (605)-759-6158.