Following Memorial Weekend, the contractor formed up the storm sewer structures so that they could pour them throughout the week. The storm sewer structures are estimated to be poured by the end of the week in which the contractor would then begin installing the underdrain. Once the underdrain is installed, concrete surfacing will follow.
Click here to review the Updated Phasing Map
If you have any questions or comments regarding this project, please do not hesitate to reach out to Josh at (605) 759-6158.
Contractor connecting water services throughout Phase 4.