Throughout the week sanitary sewer was installed in Phase 1 which they are on pace to be done with by the end of today. Water Main and Storm Sewer is starting to get installed on Phase 1 which will continue throughout the next week. Removals began and finished in Phase 2 on Wednesday the 31st of May. Access will be maintained for North Academy Street as well as Sunset Circle from the West or East side of 1st Avenue until a temporary access is in place. Temporary water will be getting installed early next week for residents in Phase 2. In the upcoming week the contractor plans on installing sanitary sewer in Phase 2 as well as getting watermain and storm sewer installed throughout Phase 1.
If you have any questions or concerns about the project don't hesitate to contact Josh Thier at (605)-759-6158 or jthier@stockwellengineers.com.
Removals completed in Phase 2