Phase 1 is almost all wrapped up with utilities as they are finishing installing Storm Sewer and the Storm Sewer boxes. In the upcoming days Sanitary Sewer will begin to get installed in Phase 2 which will continue throughout the week followed by Storm and Watermain Sewer. The contractor is estimating that Phase 1 excavation will start at the end of this week or early next week which will be followed by the underdrain. It is also estimated that the concrete, at the earliest, would begin July 5th which would include curb and gutters, sidewalk, driveways and driveway approaches.
Storm Sewer Installation on Academy Street
Comentários