Throughout the past week, the contractor installed the underdrain and began installing base course in Phase 4. This week with the rain and unpredictable weather, the contractor hopes to begin concrete surfacing. Concrete surfacing is estimated to wrap up in the beginning of July. If you have any questions about driveways/approaches, please do not hesitate to call Josh at (605) 759-6158. The contractor is planning to have Phase 4 substantially complete by July 10th. When Phase 4 is substantially complete the contractor will begin removals in Phase 6.
Click here to review the updated phasing map.
If you have any questions regarding this project, please do not hesitate to call Josh at (605) 759-6158.
Contractor Paving 2nd Avenue between Academy Street and Garfield Street.
Comentários