July 27th Construction Update

This week construction has been in full swing. The concrete crew will be starting driveways, approaches, and sidewalks in Phase 1. Once all of the concrete work is done, gravel will be shaped up in preparation for Asphalt which is estimated to start on August 10th. In Phase 2, storm sewer structures are wrapping up and will be followed by unclassified excavation. All underground utilities are completed in Phase 2 apart from the underdrain which will begin next week.


Removals in Phase 3 were completed earlier this week. The contractor plans to start with Sanitary Sewer which will begin on Elm Street at Fourth Avenue and end at First Avenue. Once the underground utilities begin, Phase 3 will be closed to traffic including the temporary access from the Alley.



If you have any questions regarding the project please do not hesitate to call Josh at (605)-759-6158.