July 25th Construction Update

Phase 4 is now open to traffic as the contractor finished paving Rummel Drive earlier this week! Today, the contractor completed removals so Phase 6 is now closed to traffic and will remain closed until construction is substantially complete. Sanitary Sewer will be the first utility that will be installed which will take throughout all next week. The contractor is estimating construction to be complete in early September.


Click here to review the updated Phasing Map.


If you have any questions regarding this project, please do not hesitate to reach out to Josh at (605) 759-6158.


Contractor Paving along Rummel Drive.