top of page
Josh Thier

August 7th Construction Update

Throughout the past week, construction has been progressing in three phases. Concrete work is underway in Phase 1, the contractor is estimating to be done with concrete work by the end of this week which will be followed by topsoil, final grading, and asphalt. Storm sewer structures have all been poured in Phase 2 which will be followed by unclassified excavation and the underdrain throughout the next couple of weeks. Once the underdrain is in place, the concrete work will begin in Phase 2 starting with curb and gutter. Sanitary sewer is currently in progress in Phase 3 and once the sanitary sewer is complete the contractor will go ahead and start to install watermain followed by storm sewer.


If you have any questions or concerns regarding the project, please contact Josh at (605)-759-6158

4" Sanitary Sewer Service installation on Elm Street.

56 views0 comments

Recent Posts

See All

Comments


bottom of page