The project has been progressing despite the heat this week. The contractor is estimating that top soil will begin towards the end of next week. While the contractor is placing 6" of topsoil, the street will be closed to thru traffic in the sections they will be working in.
In Phase 2, the aggregate base course, 12" of gravel, will continue until Tuesday of next week. The concrete crews will be prepping for the curb and gutter starting on Tuesday the 29th of August. Once the curb and gutter is complete, the concrete crews will begin to form up driveways and approaches followed by the sidewalk.
Phase 3 utilities are now complete as the contractor will now begin dirt work throughout the phase. This will include starting unclassified excavation on Wednesday the 30th of August. The contractor will start on the underdrain once unclassified excavation is complete.
Removals in Phase 5 have been completed on Thursday. The contractor will begin to hook up temporary water services early next week. Once the temporary water services are in place the contractor will begin the sanitary sewer.
If you have any questions regarding this project, please do not hesitate to call Josh at (605)-759-6158.
2" top lift of asphalt on Academy Street